What access width is required?
There is no universal gate width. The answer depends on the actual components, their packaging, the route and the space needed to move them.
Check the complete routeGarden room delivery access
A garden room can fit the plot and still be difficult to deliver. Gate width is only one measurement. Record the complete route, match it to the actual components and ask the supplier to confirm its handling plan before you commit to a configuration.
At a glance
There is no universal gate width. The answer depends on the actual components, their packaging, the route and the space needed to move them.
Check the complete routeA route through the house, an agreed neighbouring route or a professionally assessed lift may be considered. None is automatically available.
Compare conditional approachesAsk for labour, protection, removals, equipment and reinstatement to be priced separately, with the agreed assumptions recorded.
Get the scope in writingStart at the proposed unloading point and finish at the working area around the building. A nominal gate size or a photograph of the empty garden cannot establish delivery feasibility.
Ask how the selected office or pod arrives: a complete unit, prefabricated panels, smaller components or materials assembled on site. Flat-pack delivery still includes parts that cannot be reduced, such as panels, glazing and doors. An on-site build also needs access for materials, tools and equipment.
The Green Retreats FAQ gives a representative example: roof and floor panels are 1m wide, and a 3m-deep building typically has a panel 3–4m long. Its design consultant assesses side or through-house access. This is the supplier’s general example, not a confirmed component schedule for every current model or a minimum gate width.
Little Green Rooms describes prefabricated panels and a survey of the vehicle-to-site route. Oeco builds on site but flags narrow or twisting paths and low overheads, and requests nearby parking for a large van. These statements identify checks to make; none confirms your route or an extra-cost allowance.
Request the exact selected model’s largest indivisible components, their packaged dimensions and weights, any carrying frame, and the proposed people/equipment requirements. Do not assume that the longest, widest and heaviest component is always the same item. Record the supplier’s handling-space allowance rather than inventing one.
Number each pinch point on a sketch. Photograph it in both directions and include a visible measurement where practical. Measure the clear space between obstructions with doors or gates in their proposed delivery position. Include hinges, handles, drainpipes, eaves and thresholds.
| Location | Measure or describe | Decision to obtain |
|---|---|---|
| Road and unloading | Restrictions, available space, surface, permitted times and distance to the first opening. | Vehicle, unloading/staging method and who arranges any required permission. |
| Each gate or doorway | Clear width and height, threshold and projections with the opening in its delivery position. | Component and handling clearance; any authorised temporary removal. |
| Passages and turns | Widths before and after the corner, turning space, headroom and overhead obstacles. | Whether the component can be moved through; what site check or template is appropriate. |
| Steps and slopes | Step count, each rise and tread, widths, landings, slope, surface and overhead restrictions. | Weight, handling method, equipment and additional labour required. |
| Garden and work area | Remaining carry distance, soft ground, planting, storage/staging and working space. | Protection, assembly access, waste route and reinstatement. |
For each numbered point record: clear width / height: ____; projections: ____; turn or level change: ____; surface: ____; distance to next point: ____; photograph reference: ____; installer decision / outstanding check: ____. A tape measurement records geometry; it does not certify safe handling.
This is an invented route, not a surveyed customer installation. It has a 0.82m clear gate, a 0.9m passage, a right-angle turn, three steps and then another 18m carry to the work area. Consider a hypothetical panel measuring 2.4 × 1.2 × 0.15m. Its weight, packaging and handling method are unknown.
The 0.15m thickness is below the gate width, but that does not establish rotation at the corner, clearance beneath an overhang or safe movement up the steps. Turning space, headroom, step sizes and handling clearance still need assessment. No delivery price follows from these dimensions.
The useful result is a survey request highlighting the turn and steps. Ask the supplier to demonstrate the proposed route, using a template if appropriate, and confirm any change to panel size or assembly sequence before manufacture. Compare an alternative made from smaller pieces on its complete installed scope and programme: more site assembly, deliveries or finishing may change the quote.
If there’s no side entrance, show the supplier the route through the house and any alternatives. Ask which route they can assess for your chosen components and what conditions would apply.
| Approach | What must be resolved |
|---|---|
| Existing side route | Every opening, corner, overhead obstacle, level change and handling area; any temporary removal and reinstatement. |
| Through the house | Internal doors, turns, ceilings, flooring transitions, stairs if relevant, final exit, protection and occupant access. |
| Neighbouring or shared route | Actual access rights and required agreement, timing, route condition, protection and responsibility for damage or reinstatement. |
| Professionally assessed lift | Feasibility, competent planning, equipment and location, relevant permissions, responsibilities and a site-specific quotation. |
Walk the whole route with the installer before ordering. Include the front entrance, internal door openings, tight turns and the final garden exit. Identify places where materials could be set down and surfaces or fittings that need protection. Do not assume removing a door solves a turn farther along the route.
Agree who moves furniture, supplies floor and frame protection, removes/refits permitted items, cleans up and deals with damage. Record working hours and how occupants can use the home while deliveries take place. Mention children, pets or mobility needs that affect that plan, without including unnecessary personal details in enquiries.
Before offering the installer a route through a neighbour’s gate, along a shared passage or across a boundary, check who can authorise its use. Establish the required permission or access arrangement, keep it in writing and tell the installer its limits. Do the same for any proposed use of a road or public space.
HSE’s lifting guidance calls for competent planning, appropriate resources and attention to the foreseeable risks. Ask the responsible contractor to define the feasibility assessment and the necessary permissions before you accept a method or price.
A crane is not a guaranteed solution for a house without side access. This guide does not select lifting equipment, prescribe a lift or estimate its capacity or cost. Keep any proposed lift conditional until the competent team has confirmed the site-specific arrangements.
Use the printable fields on this page or download the matching plain-text worksheet. Keep the completed sheet, numbered sketch, photographs and supplier confirmation together; the sheet itself is not approval to deliver.
Project / selected model: ____; route sketch version / date: ____; supplier / survey contact: ____; proposed unloading point: ____; quote reference: ____. Attach the numbered measurements from the first section.
| Record | Supplier-confirmed detail |
|---|---|
| Component and model | ____ |
| Packaged length × width × thickness | ____ |
| Weight / carrying frame or other equipment | ____ / ____ |
| People, handling space and method | ____ |
| Route check / unresolved point | ____ |
| Evidence reference / confirmed by / date | ____ / ____ / ____ |
Ask whether a site visit or further evidence is needed; a remotely supplied sketch may leave important gaps. Keep confirmation tied to the selected components and route version. Report changes such as a new gate, altered parking, landscaping or a different product before delivery.
| Line to complete | Agreement to record |
|---|---|
| Parking, unloading and permissions | Location, times, vehicle requirements, permissions and who arranges them: ____ |
| Additional carrying labour and equipment | Method, people/equipment provision and confirmed carry route: ____ |
| Temporary removals and reinstatement | Agreed items, authority to remove, removal/refitting owner and completion standard: ____ |
| House and garden protection | Floors, frames, surfaces, planting, furniture, preparation and damage procedure: ____ |
| Occupants, working hours and route availability | Agreed access arrangements, staging and responsibility for keeping the route available: ____ |
| Waste, clean-up and later access | Waste route, disposal, clean-up, making good and access for maintenance: ____ |
Alongside every line enter: responsible party: ____; permission or document reference/date: ____; status (included / priced extra / excluded / unknown): ____; amount / VAT basis: ____; unresolved action / owner / due date: ____. An unknown charge is not £0. A feasible route is not necessarily included in an advertised installation price.
Send the same route information to the groundworks and electrical contractors. Panels are only part of the job: soil and waste may need to leave, and tools and replacement materials may need access later. Coordinate that work with the foundation survey and service installation.
Accepted route / component version: ____; written confirmation reference / date: ____; outstanding conditions: ____; change and aborted-delivery terms reference: ____. Ask for any remaining conditions to be resolved before relying on the proposed delivery arrangement.
Prepare your private supplier brief and keep the access worksheet alongside it. Our planner sends no enquiries or measurements to installers. Use the quote comparison guide to reconcile access extras, or the Bristol supplier guide for independent contact routes.
Garden Building Guide checked the linked primary sources on 20 November 2026. Supplier descriptions are representative published process information, not verified delivery plans for a particular model or property. The route and panel dimensions are an original fictional example; the diagram is not to scale and performs no collision or manual-handling assessment. No site was surveyed, supplier contacted or lifting operation designed. The worksheet records questions and written responsibilities; actual feasibility remains with the supplier and competent delivery/handling team.