Ask for the complete support design

Ground screws for garden rooms

A ground-screw quote should explain what supports the finished floor, from the frame down to the ground. Give each bidder the same room drawing and survey, then compare what they’ll design, supply and verify.

Sources checked 21 November 2026

A support head below a garden-room floor frame.

What should a ground-screw quote include?

Give the designer and installer the same brief

Record the site findings, design responsibility, acceptance evidence and required aftercare. Use one copy for each proposal on the same drawing and site assumptions.

A screw proposal needs to explain which building and loads it supports, which ground evidence was used and who designed the screw, head, frame and connections as one system. Ask how the intended use, partitions or unusually heavy equipment enter the brief. Agree the proposed floor datum and entry threshold before accepting the base. Ask what testing is appropriate, what written acceptance the designer requires and what the installer supplies for the completed positions.

Screw Foundations UK describes static ground-screw testing with a load and displacement report and installation torque monitoring for helical piles. Ask what evidence the named designer specifies for the chosen product and ground, and who will interpret it. Use the accepted design and test criteria for the actual room.

RADIX’s West Linton lodge case describes testing and 66 screws across the lodge, decking and hot-tub area. The count refers to that combined design. Ask for the schedule and evidence for your own project.

The Romford railway walkway provides a UK example of the paperwork. Its designer selected the Krinner KSF V using the predicted loads. The contractor reports that the tested working and trial screws passed the site tests. The design certificate lists separate compression, lateral and tension test records. The published copy does not show the underlying test sheets. Ask who will supply the corresponding drawings, acceptance criteria and results for your project. The Romford system and test loads belong to that walkway. Track Screw, Romford accessible walkway foundations.

Can the team reach and assess the ground?

Give the designer an access plan, levels, approximate known drains and services, records of fill or prior excavation, trees and neighbouring structures. Find out what still needs investigating and who will organise it safely. Before installation starts, agree what happens if access proves difficult, the team finds an obstruction or unexpected ground, or a result falls outside the proposed criteria. Record who stops and who can revise the design, then ask for the revised design and quote before proceeding.

Ask the team how it will identify buried services, ground conditions and adjacent structures. HSE excavation guidance for Great Britain. For structural regulatory guidance in England, see Approved Document A.

Compare screws, pads and concrete

  • Screws and frame. Ask for the exact product, ground evidence and installation record.
  • Designed pads or piles and frame. Ask how each support bears on the ground and connects to the frame.
  • Slab. Ask for the designed excavation, edge detail and confirmation that the base is ready for the room.

Compare screw and frame, designed pads/piles and frame, and slab against the same room drawing and site survey. Ask each bidder for preparation, supporting system, frame/interface, floor level and step, spoil, protection, testing/acceptance, maintenance and reinstatement. Some parts can be quoted and others may depend on investigation. Keep both visible. A choice can only be made once a competent designer accepts the selected system for the site and intended room.

Compare three foundations on one room drawing and site survey
Scope to recordScrews and frameDesigned pads or piles and frameSlab
Survey and preparationGround investigation, soil and obstructions at proposed screw positions.Ground evidence and proposed formation at each support.Ground evidence, excavation extent and formation approval.
Access and spoilAccess for installer and equipment. Price clearing, spoil and making good.Access for forming the supports. Price spoil, delivery and reinstatement.Access for excavation and material deliveries. Price spoil and reinstatement.
Named support and connectionExact screw product, head, frame and connection drawing.Individual bearing decisions, pads or piles, support heads and frame connection.Designed excavation, slab and edge detail and connection to the room.
Finished floor and thresholdScrew head, frame and finished floor levels on one drawing.Support, frame and floor datum with the step into the room.Slab, floor finish and threshold levels and readiness to install the room.
Testing and evidenceDesigner’s selected test and records, including the accepted installation record.Designer’s checks on bearing and as-installed support positions and bases.Designer’s checks on formation and specified inspection or readiness records.
Price and open workState what the installer prices and who resolves investigation, tests and deviations.Price supports, frame and access. Name who resolves open ground or preparation work.Price earthwork, slab, protection and interface. Name who resolves open quantities.
Final acceptance and aftercareDesigner accepts completed system. Agree inspection and maintenance access.Designer accepts the installed bearings and frame. Agree aftercare and upkeep.Designer accepts the slab and interface. Agree readiness, aftercare and upkeep.

Record exactly what the installer includes and who supplies the information still missing when you compare quotes.

What supports the choice of base?

Ask the installer to record the ground conditions, design assumptions and testing included in the screw price.

Open the private project planner

Sources and checks

The provider materials illustrate types of records to ask for. The project designer chooses the support system, investigation and evidence needed for the actual load and site. Approved Document A refers to England. HSE is the Great Britain source used for excavation context.

  1. Screw Foundations UK load testing — Provider’s description of static ground-screw testing and helical-pile torque monitoring. Checked 21 November 2026.
  2. RADIX West Linton lodge — The provider’s attributed case and its combined lodge, decking and hot-tub support scope. Checked 21 November 2026.
  3. HSE excavations — Great Britain context on ground conditions, structures and service checks. Checked 21 November 2026.
  4. Approved Document A — England guidance on structural loading and foundations. Checked 21 November 2026.
  5. Track Screw, Romford accessible walkway foundations — Named system, design records, contractor-reported test outcome and references to separately listed test documents for one railway project. Checked 21 November 2026.