Confirm the route to the base
Garden room crane delivery
Will the supplier leave the room beside the vehicle or place it on the base? Give the supplier and lift provider the same drawing and load details so each can confirm which part of the move they’ll handle.

Who will plan the lift and place the room?
For a site behind a garage, give the providers a drawing that identifies the obstruction, street approach, proposed unloading point and final base. Ask the building supplier for the exact model, dimensions and weight of the load in its proposed delivery state, including any fit-out or packaging. Mark structures, overhead services, trees, boundaries and ground records for the competent lift planner. Ask the planner to confirm whether a feasible crane setup can reach the surveyed final base over the garage with the selected load. Ask what evidence they need to assess ground suitability and bearing at the proposed setup.
HSE guidance for Great Britain puts planning, supervision and execution with the crane user unless the crane company expressly assumes those duties under a contract lift. Confirm the written scope and named competent people. The appointed provider assesses the ground and establishes the method, equipment and safe operating conditions.
Ainscough’s contract-lift description is an example of a provider taking on agreed lift duties. Ask who owns the survey, permits and required information under your proposed scope.
Bristol’s crane licence applies to use on or over the adopted highway. Placing the crane on the highway also requires a road-space booking. Check the rules for the actual address and name who obtains and manages permissions.
Does each delivery quote reach the same place?
Get the quote in one place
Use the same load information and access sketch with each provider. Mark the unloading point and the final position on the sketch. Ask who will confirm and price any move between them.
Ask for separate transport, crane or lift service, survey and planning, personnel, highway or traffic management, access protection, final positioning, ground protection and reinstatement lines. Clarify what happens if the room is delayed, weather prevents lifting or the route is unavailable. Confirm which party supplies and prices the lift information and final placement. A total without clear stop, cancellation and responsibility terms leaves room for unpriced work.
Keep the quotation, permissions and completion scope with the written quote comparison.
Could the room arrive in smaller panels?
- Unload then place. Confirm the handoff and quote for the second move.
- Contract lift. Get a named and documented lift scope through to the base.
- Build from sections. Have the supplier check the packaged route and price assembly.
- Revise the room or site. Update the room use, clearances and permissions before repricing.
| Option | Feasibility evidence | Placement and priced scope | Named decision or open question |
|---|---|---|---|
| Assembled unload then separate placement | Building supplier’s selected load and confirmed unload point. Placement provider assesses the rest. | Price transport and unloading, then any separate move and positioning on the base. | Agree who takes over between the vehicle and base and who accepts final position. |
| Assembled placement by contract lift | Named provider’s survey, documented scope and required consents. Feasibility remains provider-owned. | Ask who prices survey, road space and traffic arrangements, lift and final position. | Confirm who supplies load and ground information, competent staff and completion evidence. |
| Sectional build on site | Selected packed panel dimensions, handling route, protection and access agreement. | Quote transport, handling and staging, assembly, finishing and return visits. | Confirm who takes delivery, stores sections and signs off the assembly. |
| Revise the room or location | Revised dimensioned drawing, use, access and approval check. | Reprice the revised room, delivery, installation, base and services. | Name the person who confirms the new brief and layout, and set a quote date. |
Hully’s delivery page says some larger or glazed pods are unloaded beside the vehicle. The move to the base is a separate responsibility in that scope. Its sectional offer has separate wording on delivery and installation. Ask which selected contract covers unloading, movement and final positioning for your exact model.
Related guides
Sources and checks
The sources describe responsibilities and examples of supplier delivery scope. The named competent provider establishes whether a lift is feasible, what it needs and when to stop. The highway example covers Bristol’s adopted highway.
- HSE lifting operations — Great Britain guidance on competent lifting and the crane-user and contract-lift responsibilities. Checked 21 November 2026.
- Bristol crane licence — Adopted highway licence and separate road-space booking for crane placement. Checked 21 November 2026.
- Ainscough contract lift — Provider’s published scope for assuming agreed lifting duties. Checked 21 November 2026.
- Hully delivery and installation — Selected model limitations, delivery handoff and sectional provision. Checked 21 November 2026.