Give the electrician a brief
Electricity for a garden office
Give the electrician a sketch of the route from the house and a list of equipment you’ll use together. Ask which connections, tests and repairs to paving or lawn the price includes.

What to show the electrician
Give each electrician the same brief
Record equipment positions and use, the drawing revision and the connection boundary agreed with the room supplier.
List the two desks or other work areas, lighting, screens and chargers, network gear, heater or cooling and any kettle or water heater. Record the nameplate input where you have it and say what is likely to run together, including future equipment. Mark proposed positions and keep the heater and appliance demands visible even when the room comes with sockets. Ask the electrician to obtain and assess the house supply information safely and define the work up to, and inside, the garden room. Ask the electrician to assess the condition and ratings of the existing equipment and the new loads. A spare-looking breaker space alone tells you little about capacity. See Approved Document P, paragraph 1.7(a).
Oeco’s order process illustrates how internal fittings and testing can be scoped separately from the house connection. Ask for the boundary in the written quotation for your room.
Ask how the work will be inspected, tested and documented. In England, Approved Document P sets out Part P’s scope, including domestic outbuildings that share a dwelling supply. Confirm the applicable notification and compliance route. GOV.UK competent person scheme guidance describes one route for eligible work.
The IET edition checker lists BS 7671:2018+A4:2026 as the current UK Wiring Regulations edition on 21 November 2026. Ask the electrician to record the standards and requirements for the installation.
Compare trench and alternative routes
Show paving, lawns, gates, structures, known services and difficult-to-restore surfaces on the same drawing. Ask who coordinates the separately designed data route and who can reach it for maintenance.
| Route to quote | Installer and site checks | Restoration and handover |
|---|---|---|
| Excavated crossing of paving and lawn | Have the competent team locate services, assess access and quote excavation, protection and spoil separately. | List paving and lawn reinstatement separately and name who restores each surface. |
| Potential existing or maintainable non-excavated route | Have the electrician assess suitability, protection, rights, approvals and future access. | Identify each penetration and any surfaces disturbed. Name who seals, restores and maintains them. |
Give the team the available service records and photos. Leave service locating and digging to competent contractors. HSE excavation guidance for Great Britain.
What does the quoted total leave out?
Compare the complete electrical scope
Beside each item, note where the price came from, its VAT basis, whether it’s confirmed and who will do the work. List any unpriced board or supply changes next to the subtotal.
Ask for survey and design, supply or distribution work, terminations, groundworks, spoil, restoration, testing and applicable compliance as named parts of the quote. If the electrician specifies armoured cable, record its price and the associated protection and installation scope. Compare costs on the assessed route.
| Scope | Price state | Amount |
|---|---|---|
| Design and installation | Priced including VAT | £1,100 |
| Reinstatement | Provisional allowance on the same assumed VAT-inclusive basis | £500 |
| Provisionally priced subtotal | Priced scope plus current allowance | £1,600 |
| Distribution board work | Unpriced. Electrician to assess | Open |
Replace the allowance when the final reinstatement quote arrives. Keep the original in your records and use the current amount once in your subtotal.
Take the written scope to the quote comparison.
Complete Builds reports a final electrical cost of £2,400 for one garden office in Fareham. That line includes an 18 m supply run, lighting, sockets and Cat6 data. The builder records the cable trench in a separate £3,400 groundworks and base item, and heating and controls in a separate £800 item. The electrical line has no stated VAT basis. Ask your electrician to show those boundaries in your own dated quote. Complete Builds, Fareham garden office cost breakdown.
Related guides
Sources and checks
The comparison uses one builder-reported final electrical cost and a separate fictional VAT-inclusive quote. The dated guidance and IET edition checker provide context. The electrician assesses and designs the route for the actual site.
- England Approved Document P — Scope of relevant domestic outbuildings and notification and certification context. Checked 21 November 2026.
- IET BS 7671 edition checker — Current Wiring Regulations edition at the checked date. Checked 21 November 2026.
- GOV.UK competent person scheme — Registered installer route where applicable. Checked 21 November 2026.
- Oeco order process — Example boundary between internal installation and actual house connection. Checked 21 November 2026.
- HSE excavation guidance — Great Britain context for buried services and competent excavation planning. Checked 21 November 2026.
- Complete Builds, Fareham garden office cost breakdown — Builder-reported final electrical and related cost lines, route length and scope for one completed English project. Checked 21 November 2026.