GARDEN ROOM INSTALLATION PROGRAMME Project, postcode, model and drawing revision: Contract / quote revision and agreed delivery approach: Record planned and actual dates only when confirmed. For each stage say whether the timing uses working or calendar days, who decides if the weather allows work to start, and who rebooks it. FICTIONAL DEPENDENCY EXAMPLE After survey, agree the drawing and written order. Manufacture and base preparation can run in parallel where agreed. Delivery needs both releases and confirmed access. Use either the assembled placement branch or the sectional assembly branch. Finish and connect before commissioning, testing and handover. Copy the rows and replace roles with names. Stage | Predecessors | Named owner and evidence to confirm | Planned start/end | Actual start/end | Working/calendar basis | Weather check | Consequence and rebooking owner 1. Survey | Start with measured site, route, ground and services. | Surveyor and trades confirm dated findings. | | | | | 2. Design and drawing release | Survey findings and permissions or approval responsibilities agreed. | Designer and client confirm drawing, revision and stage release. | | | | | 3. Approved order | Agreed drawing and price, specification, changes and supply scope. | Contracting supplier confirms written order and procurement availability. | | | | | 4A. Manufacture and delivery release | Approved order and what the supplier needs to start. May run alongside 4B. | Supplier confirms completed or packed room/components and release. | | | | | 4B. Site preparation and approved base | Agreed base drawing and any preparation and access clearances. May run alongside 4A. | Ground team and room supplier confirm inspection and base readiness. | | | | | 5. Arrival | Both 4A and 4B released, with surveyed route and booking confirmed. | Delivery team confirms arrival and unloading responsibilities. | | | | | 6A. Assembled pod placement | After arrival. Selected unload, movement and position agreed. | Placement provider confirms final position and installation stage. | | | | | 6B. Sectional assembly | After arrival. Selected staging, assembly and protection agreed. | Room team confirms assembly and outstanding finishes. | | | | | 7. Finish and connect | After the selected branch, 6A or 6B. | Named installers and service trades confirm finish, house power and data, and plumbing if selected. | | | | | 8. Commission and test | Finishes and relevant services ready. | Trades confirm commissioning, tests and applicable separate compliance records. | | | | | 9. Handover and readiness for use | Commissioning evidence, documents and agreed remaining work. | Room team and owner confirm use, snags and assigned follow-up. | | | | | PENDING RELEASES Manufacturing delivery release and contact: Approved base readiness and contact: Surveyed access and booking: Rebooking decision, new date and affected trades: